Fremont Union High School District Adult Education & District Office Improvements - Cupertino, CA
Category: Schools
Overall Area: 33,400 ft²
Services Provided: Commissioning
Completion Date: 2022
Owner: Fremont Union High School District
Architect: Quattrocchi Kwok Architects
Contractor(s):
General Contractor: Blach Construction
Mechanical/Plumbing: Paragon Mechanical
TAB: Pacific Test and Balance
Controls: Syserco
Electrical: Best Electric
Project Description
The Fremont Union High School District Adult Education and District Office project involved significant improvements to the new district office building and classrooms, along with associated utilities and related site work. Classified under occupancy types A-3 and B, and construction type V-B, this project was completed in 2022 and adhered to Title 24 Commissioning and CALGreen codes.
Pragmatic Professional Engineers managed the commissioning through Eichler Associates Inc. for the new HVAC equipment, lighting controls, and plumbing system. Key features of the project include:
HVAC System: Installation of electric heat pumps, VRF fan coil units with branch selector boxes, VRF energy recovery ventilators, ductless split system cooling-only heat pumps, and exhaust fans.
Lighting Control System: Implementation of Wattstopper controls.
Plumbing System: Installation of electric water heaters.
This project aimed to enhance the operational efficiency and sustainability of the district office and adult education facilities, providing a modern and conducive environment for both administrative and educational activities.